Unread postby collexions » Sun Nov 5, 2017 3:19 pm

Thought I'd share the latest forecasts of NR's active projects and their associated commissioning dates:

22/01/2018 - Huddersfield-Bradford Recontrol: Stage 1 - Heally Mills & Huddersfield
29/01/2018 - Blackpool-Preston Resignalling & Recontrol: Stage 1 - Preston-Kirkham-Blackpool(South)
26/03/2018 - Blackpool-Preston Resignalling & Recontrol: Stage 2 - Kirkham-Blackpool(North)
26/03/2018 - North Wales Coast Resignalling & Recontrol: Stage 1 - Chester-Llandudno Jnc. (excl)
09/05/2018 - Wavertree Resignalling & Recontrol: Stage 2&3 - Halton & Ditton Stage
27/03/2018 - Ferriby-Gilberdyke Recontrol
20/10/2018 - Huddersfield-Bradford Resignalling: Stage 2 - Halifax (Hebden Bridge, Milner Royd, Halifax, Bradford Mill Lane SBs)
31/12/2018 - Newhaven/East Coast Resignalling
31/12/2018 - Wavertree Resignalling & Recontrol: Stage 1 - Allerton & Speke Stage
31/03/2019 - Aberdeen-Inverness Resignalling & Recontrol: Stage 2 - East interventions - 31/03/2019 (Dyce & Inverurie SBs)
31/03/2019 - Norwich-Lowestoft Resignalling

Several others forecast for Xmas 2018, but they're large schemes and aren't yet live, so sceptical that they'll make end of CP5 (April 2019).